TAS Portal

← Atenvia planning · Baseline findings

Atenvia workshops, discovery and planning timeline

Decision review · 19 November 2026

Version 2026-11-19-easmed-transcript-review-v1. Workshops, product and technical discovery, and planning remain the current engagement under timeline v4. Easmed owns funding and appointment of any future build team.

In the 17 November retrospective, Audrey planned to present three engagement options to Easmed on 26 November, 2–3 pm Singapore time. Shane and Kedar were expected to join, subject to calendar confirmation. The working team has recorded the options discussion. Easmed's choice, decision owner, build appointment and governing grant obligations remain open.

At the 11 November internal kickoff, the team agreed to seek stakeholder sign-off on the vision, problem, users and success before design. Clinic-scoped access, dashboards and patient records were candidates for discovery. The earlier January go-live and February grant dates were internal scheduling assumptions and are historical. 17 November retrospective transcript · 11 November kickoff transcript excerpt · Product Home · EAS-89 · EAS-16 · Easmed decision timeline.

Initial desk baseline · 12 November 2026

Technical and product baseline pack, version 2026-11-12-atenvia-baseline-v1, records the source/branch inventory, bounded local build checks, current/reported/proposed data flows, product conflicts, measurement definitions and next validation needs. The desk review is available now; the proposed 27 November stakeholder/source-owner review remains open. No application code, live integration or infrastructure was changed. The planning schedule and scope remain as stated below.

Version: 2026-11-12-atenvia-timeline-v4
Updated: 12 November 2026 following Shane’s direction to baseline the technical position before broader product discovery.
Scope: Workshops, product discovery, technical discovery and planning. No MVP build.
Status: Capacity-based recommendation; workshop bookings, IMDA requirements and final planning endpoint require agreement.

We will help Easmed define the product, understand the technical constraints and prepare a plan for a future delivery team. Easmed should secure additional resources for building in parallel. Our scope is planning; securing a team does not automatically add implementation, integration development, production deployment or pilot operation to this engagement.

The initial start remains 19 November after the agreed one-week shift. Technical discovery and an initial current-state baseline now lead the sequence, with a proposed baseline review on 27 November before broader product workshops. Timeline/access review remains 24 November, emerging priorities review 7 December and initial findings review 11 December. The previous December–February build, UAT, pilot and submission schedule is withdrawn rather than shifted into a new delivery commitment. Historical meeting dates and grant dates are not moved by this change.

Capacity and working assumptions

Shane and Raena each have 10 engagement days per month. Reserving 15–20% for the Snoraire handover leaves 8–8.5 days per person per month for Atenvia: 16–17 person-days combined. Plan against 8 days each, or 16 combined, rather than depend on the upper end. As a rough four-week model this is about 2 days each per week, not continuous full-time availability. November must be prorated from the start date and existing commitments checked; there is no assumption that a full month’s days remain after 19 November.

The calculation assumes the 15–20% reserve applies to each person’s 10-day allocation. Atenvia time includes workshops, preparation, interviews, analysis, documentation, stakeholder follow-up, coordination and reviews. A joint session consumes both people’s allocations. Meeting time is not additional capacity.

Kedar is a fractional UI/UX designer with limited expected Atenvia involvement. Design is not a delivery dependency: use workflow maps, rough screen sketches and the existing reference material for discussion. Ask Kedar for a targeted review only if needed and capacity is available. Do not commit to a polished prototype or full visual design.

Easmed management, Pam, clinic users and technical/data owners are assumed available, as instructed. This is a scheduling assumption rather than booked access or confirmed decision authority. Raena leads stakeholder/workflow discovery; Shane leads technical discovery and product/technical synthesis, with priorities agreed together. These are recommended working roles, not new contractual allocations.

Window Product/workshop focus Technical/planning focus Review output
19–24 Nov 2026 Establish the business questions, decision authority and IMDA obligations; arrange technical-owner sessions. Broader solution workshops follow the initial baseline. Gather existing code/repository references, architecture/environment records, data models, integration documents and access owners. Evidence/access inventory and agreed baseline questions; review on 24 Nov. Easmed begins securing build resources.
19–27 Nov Raena coordinates current-workflow context and source owners needed to interpret the technical material. Shane leads a timeboxed review of the existing code/architecture, systems, data flows, interfaces and API documentation. Separate demonstrated capabilities from mock UI, specifications, assumptions and inaccessible items. Initial technical baseline review on 27 Nov: current-state map, reusable assets, evidence limits, risks and access/specification gaps. This is not a comprehensive code/security audit or a promise of successful API tests.
30 Nov–11 Dec Use the technical baseline to focus clinic/TAS interviews and workshops on priority problems, workflows, exceptions and information needs. Review emerging priorities on 7 Dec and initial findings on 11 Dec. Refine feasibility questions with actual user needs. Continue documentation/access follow-up without blocking all product work on vendor replies. Prioritised product findings and updated feasibility/options register.
14–18 Dec Agree a first product planning baseline: users, outcomes, workflow boundaries, priorities and exclusions. Consolidate technical options, dependencies and the future-team resource brief against the initial technical baseline. Combined product/technical planning baseline by 18 Dec; review Easmed’s progress securing build resources.
21 Dec–1 Jan 2027 Consolidate documentation and handle asynchronous clarifications within confirmed availability. Tidy the decision/risk register and prepare outstanding questions. Holiday allowance; no critical workshop or approval is assumed in this window.
4–15 Jan Validate the baseline with users and Easmed decision makers; resolve material scope questions. Refine requirements, options, dependencies and handover material; seek feedback from Easmed’s build resources if appointed. Recommended planning/handover review by 15 Jan. Any remaining unknowns retain owners and next steps. This is not a product delivery date.

This is approximately six active working weeks across a longer calendar period, with holiday allowance. The mid-January planning endpoint is a recommendation to agree, not a new promise. The available November/December days and holiday arrangements must support the sequence. If they do not, reduce the planning package or revise the endpoint openly.

Initial technical baseline: what we need to know

Timebox the opening phase to the available November allocation. The output is a factual starting point for discovery, not a finished architecture design or engineering assurance report:

Target 27 November for an initial baseline review, subject to available material. Resource search and IMDA clarification proceed in parallel. Technical interviews support this first phase; wider product solution workshops follow it. No connector, MVP, production access change or code-based experiment is added to scope.

Working rhythm and planning budget

Recommend one substantive external session per week plus a short internal synthesis/decision review. Start with technical/data-owner sessions and baseline evidence collection; focus later sessions on product/workflow discovery informed by the baseline. Use targeted interviews or technical-owner sessions when they replace or justify other work within the same allocation. Do not assume two workshop streams require both people in every session.

For a full month, budget each person’s 8 Atenvia days across roughly 2 days of external sessions/targeted interviews, 4 days of preparation and analysis/documentation, and 2 days of coordination, reviews and follow-up. The split is a planning allowance, not a timesheet requirement; rebalance between the two people as discovery progresses. If handover exceeds the reserved 20%, reassess the Atenvia forecast instead of treating the overrun as free capacity.

Next steps · 12 November 2026

Plan version: 2026-11-12-atenvia-timeline-v4; portal/action supplement: 2026-11-12-atenvia-portal-v1. Gantt · Portal next steps. This is a manually maintained view, not a live status sync. Owners/windows below are proposed for coordination; completion is not verified.

Next step Proposed owner Target / output
Confirm the actual IMDA obligation Easmed sponsor / Gary or Ervin provides; Shane + Raena consolidate Opening alignment, 19–24 Nov: governing date, deliverables, acceptance evidence and approved variations mapped to owners.
Book initial technical-owner sessions, then product workshops Raena with Easmed Arrange before 19 Nov; access/brief review 24 Nov; initial technical baseline 27 Nov. Broader product workshops 30 Nov–11 Dec.
Assemble current-state technical evidence and brief Shane + Raena; Pam and technical/data owners contribute 19–24 Nov: outcomes, workflows, system diagrams, permitted/synthetic report samples, Zoho/vendor documentation and access owners.
Prepare prisma CLOUD demo registration details and guide review Raena coordinates Easmed’s nominated administrator; Shane reviews technical requirements 19–24 Nov: confirm subdomain, organisation, country/time zone, admin name/email. Guide review in the 19–27 Nov baseline phase; demo not provisioned, synthetic data only.
Recommend additional build resources Shane + Raena recommend; Easmed funds and appoints Begin during November discovery; review progress 18 Dec. No appointment date or vendor assumed.
Agree capacity, review dates and planning endpoint Shane + Raena with Easmed Review 24 Nov; revisit 11 Dec. Confirm Snoraire reserve, holidays and proposed January handover; Kedar’s input remains optional.

API specification availability · 12 November 2026

See the API specification/access register. Zoho has detailed public API specifications; prisma CLOUD has detailed documentation behind the supplied shared login. For AirView, CloudPAT and NeXus360, public integration material was found but no public developer-level endpoint/schema contract was located. Request their current specifications before treating credentials or an integration estimate as the next step. This is a search result, not proof that private specifications do not exist. No Easmed tenant/API entitlement is established.

prisma CLOUD API evidence · 12 November 2026

Supplement: 2026-11-12-prisma-api-discovery-v1. The vendor supplied a getting-started guide and a route to demo tenants with fake devices. Documentation access was verified; tenant/API access and feasibility remain untested. Prepare demo-registration details with Easmed’s nominated administrator, then review the documented data/access/report capabilities in technical discovery. Real patient data is prohibited in the demo. Credentials are excluded; no request was sent or account created. Any code-based validation requires separate agreement. See the API discovery record. The evidence supplement does not add build scope. Its guide review now sits in the 19–27 November initial baseline under this current sequence; capacity remains unchanged.

Parallel recommendation: Easmed secures build resources

From the opening alignment window, we will recommend that Easmed secure additional engineering and delivery resources for the future build. We can help Easmed define the capabilities needed, prepare a briefing pack and identify questions for prospective resources while discovery continues.

Easmed owns the resource appointment, funding and procurement decisions. The resource recommendation should cover technical leadership, engineering, QA/testing, deployment/security and ongoing operational support, with roles combined where appropriate. Ask Easmed to begin securing these capabilities during the November discovery window; do not wait for the January handover pack. Invite an appointed technical lead into discovery as soon as available, without making their appointment a dependency for all planning work. No named vendor or internal engineer is assumed to be appointed. Ashwin was a previously discussed option; discovery should inform any subsequent briefing or quotation.

A future build team must validate implementation effort, dependencies, capacity and delivery dates. Our planning timeline does not commit that team’s build schedule or approve its costs.

Discovery questions to resolve

Singapore B2B clinic access, patient/clinic reporting and source-report downloads remain starting hypotheses from earlier discovery. Older scheduling, clinical communication and multi-vendor proposals must be discussed and prioritised rather than inherited as approved build scope. No clinical formulas, alert thresholds or extraction accuracy are approved by this timeline.

Technical discovery means workshops, documentation/sample review, interface/data mapping and feasibility assessment. It does not include building an MVP, implementing connectors, production integrations or an operational pilot. If a code-based technical experiment is proposed, define and agree it separately before adding it to the plan.

Responsibilities

Area Planning responsibility Confirmation needed
Product management and timeline Shane leads planning and synthesises findings 10 days/month gross; plan 8 Atenvia days after handover reserve
Discovery coordination Raena coordinates stakeholders and discovery arrangements 10 days/month gross; plan 8 Atenvia days after handover reserve; stakeholders assumed available
Clinic/TAS workflow knowledge Pam and nominated clinic/TAS representatives contribute evidence Easmed confirms product owner, users and decision mandate
UX exploration Kedar contributes lo-fi flows where they help validate workflows Limited involvement expected; optional targeted review, not a critical dependency
Technical discovery Shane coordinates the questions and technical plan with nominated technical/data owners Easmed identifies available technical participants; no Jonas allocation assumed
Scope, priorities and resource decisions Easmed’s authorized sponsor/product owner Gary/Ervin delegation, budget and procurement ownership
Future implementation Additional resources secured by Easmed Separate team, scope, estimate and delivery plan

These responsibilities describe the planning model; unconfirmed participant availability remains open.

IMDA constraint and decisions still needed

Shane identifies IMDA obligations as the main deadline constraint. We need Easmed’s governing date, required product/evidence deliverables, acceptance criteria and approved variations during the opening alignment window. The local grant reconciliation identifies a historical proposal rather than the signed grant-of-record; it does not establish the current deadline. Earlier February tracking/submission references remain dated planning context.

Map each actual obligation to an owner and a dependency: our discovery/planning outputs, Easmed’s decisions and resource appointments, and the separate team’s implementation/validation evidence. A planning pack cannot stand in for a working system if the obligation requires one. Once requirements are confirmed, surface any resource or schedule gap to Easmed promptly, rather than assume that a mid-January handover leaves enough time to build.

Still to agree: the exact IMDA requirement; the recommended 15 January planning endpoint; workshop bookings and holiday availability; Easmed’s decision authority and owner for securing build resources. Stakeholder availability and the team’s monthly allocation are now planning inputs, not unanswered questions.

Sources and counterparts

This revision adds Shane’s 12 November sequencing direction: technical discovery and initial baselining first, then broader product discovery. It retains the 11 November scope and capacity instructions: planning only; a one-week shift to the initial stages; 10 days/month each for Shane and Raena with 15–20% reserved for Snoraire; limited Kedar involvement; Easmed stakeholders assumed available; and IMDA obligations as the main deadline constraint. Version 1’s MVP/build/pilot schedule remains withdrawn. Version 2’s 11 December initial review remains; the later planning windows are recommendations based on the newly stated capacity.

Earlier context, retained as dated evidence rather than current delivery promises:

Canonical counterparts: product specification, historical core-build proposal, Notion product home (separate access may be required), EAS-89 (separate access may be required) and EAS-16 (separate access may be required). Grant context: local grant reconciliation (internal working reference; not published).

The meeting summaries were read in the preceding review, not refreshed for this user-directed revision. No build execution, integration success, resource appointment or grant acceptance is established by this document. Historical source dates remain intact.