Beta release decisions
Current decisions and release evidence — reconciled 11 November 2026
Version: 2026-11-11-decision-checkpoint-v1. Password sign-in, the provisional formula, Night Notes and the bedtime reminder are approved choices under 2026-11-02-owner-confirmation-v3. Their implementation and testing remain separate acceptance work. Exact original approval dates retain the limits recorded in the owner confirmations.
The last beta assessment is 2026-11-08-beta-release-preflight-v5: hold invitations. Four preparation gates are complete; store distribution is partial and six other gates remain unfinished. Android 0.1.10/26 and iPhone 0.1.10/32 were submitted. Tester access, physical installation, overnight acceptance and operational approval remain open. Shane owns deployment and DevSecOps; Jonas supports application/build defects.
D-07 privacy research was completed on 3 November; legal endorsement and implementation acceptance remain open. Historical 28 October reviews and the 11 November invitation target do not establish a current deadline or permission to invite. Remaining product decisions include result categories/copy and the regional callback/CRM contract. No requirement, owner, acceptance criterion or ticket status is changed by this presentation update.
Read the owner confirmations (internal working reference; not published), beta checklist (internal working reference; not published) and reconciled decision timeline (internal working reference; not published).
Earlier dated planning — historical where superseded
Current owner confirmation — 2 November 2026
Version: 2026-11-02-owner-confirmation-v3. Read the current confirmed decisions (internal working reference; not published) first. Shane confirms password sign-in decided by Jonas and Shane (D-01), the current provisional formula approved last week in the Ervin meeting with ongoing Jonas testing/tuning (D-02), and Night Notes plus bedtime reminder approved for MVP last week (D-28/D-29). Exact historical dates were not supplied.
D-06/D-15/D-21/D-26/D-27/D-20 await today’s meeting confirmation. D-07 research is due Wednesday, 4 November. D-25 result hierarchy joins today’s approval priorities. Earlier conflicting approval-status and MVP-inclusion wording below is historical. Formula approval is separate from category bands, clinical/device validation and release acceptance. No ticket closes solely because these records change.
Latest decision reconciliation — 2 November 2026
Version: 2026-11-02-granola-refresh-v1. Current Excel decision log; source reconciliation and open decisions (internal working reference; not published). The workbook contains the current review log, all 19 concerns, prior decision history and source evidence. The 29 October account/password and audio-only deletion discussions conflict with earlier proposed contracts. SG Deals versus Leads and API versus form wording also need confirmation. These are recorded conflicts, not approved requirement changes. November remains an invited technical beta; January is the broader launch direction. Final approvals and acceptance evidence remain pending.
Earlier dated content in this document is historical where it conflicts with the refresh. Notion alignment is pending access; no release, implementation or clinical/legal acceptance is established here.
Management review update · 28 October 2026
Version: 2026-10-28-management-review-v1. Shennan approved these four documentation updates after reviewing the 23–28 October chat. Policy values and clinical thresholds remain open.
- Management view: lead with source UI, plain English and the 1.0/1.1/1.2 relative weights. Keep equations, simulator and API/environment diagrams available in expandable technical detail.
- Full profile: show the existing V1 Profile screen. Decide which fields are required, why each is needed and when to collect it. Prototype fields are not an approved collection list. Account signup and email verification remain the direction; SMS awaits Malaysia Twilio setup.
- January only: the proposed repeated-pattern rule is three qualifying nights in a rolling seven-day window. Define qualifying nights, missing-night handling and care wording before implementation. It is deferred to January, outside MVP scope, and is not an approved medical threshold. MVP care access is proposed after one usable night.
- Phone audio: choose automatic pruning window or low-space trigger, removal order, warning and retained report/notes fields. Protect active capture and processing, show unavailable playback accurately and prevent stale writes. Automatic pruning is distinct from manual Delete all recordings, which retains its proposed all-recordings/reports/related-night-data scope.
- Server retention: decide retention, user notification, erasure and provider exceptions for inactive accounts and sleep results, including users who uninstall. Uninstalling is not account deletion. Staging and production store no raw audio on the server; research upload retention is a separate consent/purpose decision. No retention duration or storage budget is approved here.
Earlier dated records remain historical where they conflict with this update. No implementation, device acceptance or release approval is added.
Accounts, deletion, release data and CRM flow · 28 October 2026
Version: 2026-10-28-account-data-crm-v1. Source: Shennan’s current clarification and supplied deletion-flow context. Account signup with email verification is the current direction; accountless setup is superseded. SMS verification depends on Malaysia Twilio provisioning and verification, with no committed completion date. This replaces January as a fixed SMS assumption.
Deletion proposal for the account flow
The menu contains Delete all recordings, Delete account and Logout. Delete all recordings removes every recording, report and related night data in the declared local/server scope, while keeping the account. Delete account removes the identity and governed data and revokes sessions. Logout ends the session without deleting the account. The accountless alternative is historical, not a current option.
Use a full-height confirmation sheet: Delete all recordings? “All recordings, reports and related night data will be permanently deleted. This can’t be undone. Save any reports you want to share with a medical professional first.” Buttons: Keep recordings / Delete all recordings. After confirmed deletion, Reports shows No recordings yet and Record tonight. Preserve honest pending/failed remote status, block stale retries and define the separate research/CRM erasure process. Management still needs to approve the exact deletion scope and provider retention exceptions; this replaces the audio-only-retain-report proposal as the recommended menu.
Three release/data boundaries
- Staging: internal testing; no server storage of raw recordings, playback clips or raw waveform data. Test results and approved metadata only.
- Research preview: beta features and user-initiated sleep-result uploads. Define the payload, consent, retention, withdrawal and whether any raw data is included before enabling uploads; the current direction does not specify that raw-data scope.
- Production: main app; no server storage of raw recordings, playback clips or raw waveform data. Approved structured account/results data only.
Use separate endpoints, credentials and permissions. The diagrams describe intended boundaries, not evidence that the environments are deployed or that storage/payload controls pass.
Direct CRM handoff for Thursday 29 October
Submit callback requests plus agreed sleep-result context directly through CRM APIs, not webforms. SG and MY write to separate CRM databases within their respective Leads / Deals constructs. CCC is intended to have read access to both. Confirm country selection, permitted result fields and consent, the Lead-to-Deal mapping, receipt, access roles, response promise, duplicate prevention and fallback with CCC. Decide what happens for users outside SG/MY; do not silently reroute. Singapore payment/booking is removed from this handoff approval.
Distribution and pack layout
For iOS, share the TestFlight invitation link after the build is available for external testing; Apple’s external group and beta review requirements still apply. Android needs a separate route. Apple guidance. The standalone test-plan section is removed from the meeting pack only; existing device/security/privacy/operational acceptance gates remain in the linked test plan. Timeline title: Path to 11 Nov launch.
Recording duration and score illustration · 28 October 2026
Version: 2026-10-28-duration-and-simulator-v1. Shennan sets the recording boundary to 2 hours minimum and 8 hours maximum, inclusive. Below two hours, no eligible score. Stop capture at eight hours. Audio-quality rules remain a separate requirement. These are recording hours, not measured sleep. This replaces the earlier six-hour eligibility proposal; it does not define short-session discard or recovery behavior.
Test 2h minus one second, exactly 2h, exactly 8h and the attempted 8h-plus-one-second boundary. Capture must not continue beyond the maximum. Existing three-night device acceptance gates remain unchanged; this document update is not an implementation pass.
The portal shows the recommended clamp formula as LaTeX and plain English. Its interactive scenario varies recording hours (2–8), episode minutes, a single relative sound level applied to all episodes, and a provisional scaling cap. The 8/18 dB relative bands produce weights 1.0/1.1/1.2. The default 8h, 60-minute, 12 dB scenario gives Pw=13.75% and about 40.8 points at cap 82.5. This is hypothetical, not a workbook result or a clinical-severity simulation. Moving the cap does not approve a threshold or change the production formula. 82.5 remains provisional and unapproved.
Recommended score · 28 October 2026
Version: 2026-10-28-score-recommendation-v1. Source: Shennan’s correction. Recommend the later background-relative formula with the clamp, rather than the historical 80/20 blend.
Score = 100 × sqrt(clamp(Pw, 0, 82.5) / 82.5)
Pw = 100 × sum(episode duration × mean snore weight) / recorded audio time.
Use duration-weighted snore weights 1.0 / 1.1 / 1.2 at 8 / 18 dB above background. Episode spans include quiet gaps. These are relative signal inputs, not calibrated physical loudness.
The 82.5 cap remains provisional. Confirm the final parameters, quality exclusions and missing-noise behavior, then validate on compatible recordings and supported phones. The supplied workbook lacks this candidate’s required inputs; no measured result or clinical approval is implied. Keep breathing highlights separate. The older 80/20 ring is a historical comparison only.
This supersedes earlier recommendation wording. Historical formulas, reproduced results and existing acceptance gates are unchanged.
Current MVP scope · 28 October 2026
Version: 2026-10-28-mvp-approval-v1. Source: Shennan’s direct update on 28 October, recording Ervin’s scope decisions and the team’s tagger observations. This supersedes conflicting earlier proposals; it does not select a formula or prove implementation.
- Focus the MVP on snoring. The Rest score was previously ruled out; do not reopen it for this launch.
- Do not present loudness as calibrated dB without validating every supported phone model. Relative audio features may inform research, but they are not calibrated loudness or proof of comparability across phones. Their use in the final snore formula still needs approval.
- Cough and movement are outside the MVP. Reopen either only with a clear user benefit, evidence and a recommendation strong enough to explain to Ervin.
- The team reports that the audio tagger reliably picks up coughs; movement tagging is unreliable. This is a reported capability distinction, not new independent validation or a reason to add either feature.
- Existing separately reviewed breathing highlights retain their own evidence and approval gate. They do not create a Rest score or a combined sleep score.
Older formulas and original prototype screens remain reference material. Their dB values, extra metrics and sample copy are not approved MVP claims.
Notion alignment: EAS-1, EAS-2, EAS-83, EAS-88, EAS-69, EAS-87 and the launch checklist now carry this version. The first four acceptance fields include the scope/calibration boundary. Owners, due dates, estimates and statuses are preserved. Saved text, tables and properties were read back; no ticket was closed.
MVP launch timeline · 11 November target
Version: 2026-10-28-mvp-approval-v1. This is the proposed backward plan for stakeholder approval, not a delivery commitment. Intermediate dates and assignments need agreement. The target is a controlled MVP/private-beta launch, not broad public promotion.
| Date | Checkpoint | Marketing | Development / product | CCC / regional care |
|---|---|---|---|---|
| 28 Oct | Approve the MVP | Daniel/Maha: audience, message and landing-page priorities. | Ervin/delegate: snoring scope; Jonas: estimate, supported phones and proposed freeze; Kedar: report flow. | Name country approvers and the people who will receive requests. |
| 29 Oct | Approve the care handoff | Match the care promise and country wording to the agreed service. | Confirm permitted payload, consent, country routing, receipt states and access dependencies. | Approve queue owners, hours, response time, fallback and SG payment/booking. Confirm interim SG cover. |
| 30 Oct | Proposed scope and candidate freeze | Freeze approved claims, invitation copy and required assets. | Freeze the release candidate and formula/quality configuration. Re-estimate or move the date if it is not ready. | Approve the operating checklist and named test recipients. |
| 2–5 Nov | Rehearse and collect evidence | Test the landing page and signup journey in the week of 2 Nov; verify approved UTM/events. | Run three consecutive eight-hour nights per supported phone class on 2–4 Nov; assemble evidence on 5 Nov. Check full-journey fixes. | Prove SG/MY destination receipt, retries and a human response. Rehearse failure handling and support. |
| 6 Nov | Proposed go / no-go | Approve audience, claims, channels, batch limit and the measured invitation journey. | Approve the exact build and evidence packet, including device, security, privacy, score and recovery gates. | Approve staffing, receipt proof, support hours, response promise and fallback. |
| 9–10 Nov | Final readiness check | Stage approved invitations; test every link and install instruction. | Rehearse install and rollback. Confirm no untested change has entered the approved candidate. | Confirm live queues, on-duty people and escalation contacts. |
| 11 Nov | Target: controlled MVP launch | Invite only the approved first batch; monitor signup and activation. | Release only the approved candidate; monitor recording, results, saves and failures. | Monitor receipt and first human response; pause invitations if pickup fails. |
Three approvals before launch
| Angle | Approver / coordinator | What must be approved |
|---|---|---|
| Marketing | Daniel leads; confirm the authorized marketing approver. | Approve the audience, batch size, snoring-only claims, channels, assets, signup/install journey and permitted measurement. |
| Development / product | Ervin or his formal delegate approves product scope; Jonas supplies technical readiness evidence. | Approve scope, the exact build/configuration, formula and wording, supported phones, device evidence, data/privacy/security and rollback. |
| CCC / regional care | Name the SG SCC and MY CCC approvers and their interim cover. Shane, Jonas and Daniel coordinate. | Approve country routing, consent/payload, staffing, hours, response promise, receipt evidence, SG payment/booking and fallback. |
All three approvals are required. Record Approved, Revise or Deferred, the approver, date, exact scope/build/configuration and evidence link. Name the overall release approver. No green status is inferred from this plan.
Two conflicts need decisions now: the earlier mid-November feature lock is incompatible with 11 November launch; the reported SG SCC start in mid-November needs named interim cover. Either approve an earlier feasible freeze and cover, or move launch. Do not compress the device tests or silently substitute care routing.
EAS-26/27 stays unchanged: three consecutive eight-hour release-build nights per supported phone class; at least 98% coverage; no gap over 75 seconds; Android flat memory and zero silent loss; iOS results within five minutes after reopening. A changed build, failed gate or missing regional receipt requires review and affected evidence again. Withhold invitations until the gates pass.
Version: 2026-10-26-draftpack-v1 · Prepared 26 October for Wednesday 28 October 2026. Working draft; recommendations below need approval. The recorded decision baseline remains 2026-10-26-signoff-v1.
Source: 26 October meeting record (internal working reference; not published).
Approval requests · 27 October editorial review
The decision pack puts one approval request above the options on each slide. Product authority remains Ervin or his formal delegate. Gary is a reviewer unless delegated. Clinical, privacy, care-operations and release approvals need named owners.
- Accounts: approve required fields, consent and sign-in recovery. Email OTP is the recorded direction.
- Score: approve the measure, input rules and compatible comparison before selecting a formula and scale.
- Care prompt: choose one night or a repeated pattern, then approve cutoffs, highlight rules and wording.
- Recording: approve duration, measurable quality and failure outcomes. Decide cancellation separately.
- Deletion: choose the deletion options and approve retained fields, scope, retention and failure behavior.
- Care handoff: confirm country destinations, permitted fields, receipt, response promise, fallback and Singapore payment/booking steps.
- Data: approve fields, ownership, retries, retention and deletion before enabling uploads.
- Legal: name the reviewer, complete the facts and choose the notice structure before customer use.
- Release: agree the freeze, evidence sequence, approver and invitation forecast.
- Beta: approve the first batch, recruitment owner, support and expansion criteria.
- Testing: name the build, phones, participants and reviewers. Feedback rounds do not waive EAS-26/27.
These requests consolidate existing open decisions. They do not record new approvals or change formulas or acceptance criteria. Record Approved, Revise or Deferred, with the approver, date and exact version.
Care update from the 27 October launch discussion (separate access may be required): direct API submission to Zoho is the recorded direction. Confirm Singapore SCC versus the earlier SG CS name and Malaysia CCC routing. Jonas coordinates Malaysia access with Wei Jian. Shane, Jonas and Daniel coordinate the 29 October handoff review. Access, receipt, payment/booking sequence and response promise remain open; neither 24 hours nor three days is approved. Earlier observations below retain their dates.
Actual V1 design reference · 27 October
Review the AUD’NCO V1 source prototype alongside this brief. Source provenance and screen mapping identify required changes: full accounts are not implemented in the prototype, comparisons/repeated-pattern copy differs from the 26 October deferrals, partial reports use two hours, and callback submission/receipt remains incomplete. Adding the source is design evidence, not approval of its sample numbers or rules.
The page copy received an STE-style editorial pass on 27 October (2026-10-27-ste-v1). It now explains the context and trade-offs beside each exact source screen. Source Option 2 shows separate loudness/snoring points; Kedar must align that explanation with whichever formula is approved. This is a design-consistency question, not a newly approved calculation.
Responsibilities and approval record · 27 October
Version: 2026-10-27-completeness-v1; source review and deliverable evidence (internal working reference; not published). The evening 26 October note records Shane focusing on PM and Jonas owning engineering. Shane coordinates this pack and the walkthrough; Kedar prepares design/copy. Earlier proposals for Shane to implement database/API work need reassignment or explicit reconfirmation.
The internal note reports Ervin as final product authority; Gary needs formal delegation to exercise that mandate. We need to confirm it at the 28 October review and name the clinical, legal/privacy, operational and release approvers. The expanded register includes options/trade-offs, recommendations, decision targets and affected requirements. Record the actual selected option, rationale, approver, date and exact approved version; blank approval cells remain pending. D-08 through D-10 cover mandate, cross-functional delivery and handover.
The 28 October review target is not a committed implementation deadline. Agree deadlines per decision; if an authorized decision is missing at its agreed deadline, pause the affected item and record the impact. The Notion counterparts remain unsynced (internal working reference; not published) for this supplement.
Meeting outcome and sequence
We need written choices that Kedar can show and Jonas can implement. Discuss one decision per screen: intended outcome, recommendation, alternative, risk, approver and exact acceptance example. Record approved, revise or defer; silence is not approval.
Proposed 60-minute agenda: 5 minutes on the beta and date conflict; 15 on scoring, categories and CTA; 10 on usable recording; 10 on deletion; 10 on accounts/data/CRM; 10 on legal, owners and the final decision record. This duration is a suggested agenda, not a booked meeting.
D-01 · What are we approving for V1?
Recorded: full accounts with email OTP; optional notification consent; local capture and foreground final processing; an intelligible report; care request to the correct country team. No second-phone sync is required, but ownership and identifiers must support it later. January work includes comparisons, minimum nights/averaging, trend CTA refinement and SMS verification. Social login and magic link are deferred without a committed date.
Recommendation: keep this sequence and approve a single minimum-profile contract. Require email for OTP; make additional profile fields mandatory only after their purpose and necessity are agreed. Reuse the existing auth components after verifying first-use, returning-session and deletion paths. An existing OTP plugin is not proof of a complete passwordless journey.
D-02 · Snore score formula
Current review: 2026-10-27-score-tradeoffs-v1. Dataset-backed scoring outlook and interactive portal comparison add the supplied Numbers evidence. The 145-record PSG and 13-record phone comparison reproduces 474 cached snore outputs and 33 aggregates. It favors the historical 80/20 ring on most normalized stability checks, but changes both duration definition and formula. The later relative-noise candidate cannot be fairly computed from the supplied fields. The later background-relative clamp formula is the recommendation; retain the older ring only as a historical comparator. Confirm its parameters and validate compatible inputs before release. Breathing highlights remain separate. No formula, cap or clinical band is approved. Earlier source observations below retain their dates and versions.
Local source inspected at checkout HEAD 653cf4707af83edf039a10c5e7150b3d9771618e: shared calculation (internal working reference; not published), mobile input extraction (internal working reference; not published). This is source inspection, not deployed-build or scientific acceptance. Pin the eventual candidate and save a source digest.
For episode j, let E_j be the episode’s full media-time span. For each snore starting within that episode, d_i is its duration and w_i its intensity weight. The inspected source weights snores using peak RMS minus the night noise floor: below 8 dB → 1.0; 8 to below 18 dB → 1.1; 18 dB and above → 1.2. These are signal-processing bands, not clinical severity bands.
- Episode weight = sum(d_i × w_i) / sum(d_i); if an episode has no snore duration, the source uses 1.0.
- Weighted seconds = sum(E_j × episode weight). Episode spans include quiet gaps inside the episode; this is not simply all snore-event durations added together.
- Weighted share (%) = 100 × weighted seconds / recorded audio seconds.
- Candidate score = 100 × sqrt(clamp(weighted share, 0, 82.5) / 82.5).
The 82.5 cap is explicitly provisional in source. The denominator is recorded media time, not measured sleep time. In source, missing noise floor falls back to unweighted share with a flag; non-reference detection can leave the snore score unavailable. Proposed product rule: quality-invalid, zero-duration or non-finite input shows unavailable rather than a reassuring zero. Decide whether a flagged unweighted fallback is allowed or the score should be withheld. Do not imply this is already implemented at every boundary.
Worked illustration: 480 minutes recorded and one 60-minute episode with mean weight 1.1 gives 66 weighted minutes, a 13.75% share and approximately 40.8/100. The example illustrates the mapping; it is not a moderate/severe label. Holding duration fixed, 1.2 versus 1.0 increases the score by at most sqrt(1.2), about 9.5%, before saturation.
Alternative: raw snoring-time share is easier to explain but omits the candidate’s intensity weighting. An older 1/2/4 experiment and 80/20 blend remain historical alternatives, not selected formulas or drop-in equivalents. A combined snore/pause score is outside beta.
Wednesday decision: Ervin and the appropriate reviewers accept or reject the exact candidate/version, denominator, noise-floor fallback, quality exclusions and wording. Keep EAS-83 input evidence and EAS-30 determinism/device-repeatability gates.
D-03 · Categories and care CTA
Recommendation: review the one-night approach because comparisons are deferred. Do not invent a Repeated Patterns rule while its minimum-night/averaging logic is outside beta. For V1, propose Ordinary / Unusual presentation with the third category deferred, or use three non-temporal labels if management wants three states. Both label options require approval.
| Eligible report state | Proposed automatic prompt | Manual care entry |
|---|---|---|
| Below approved snore CTA threshold; no independent highlight trigger | Encourage another night; no score-triggered care prompt | Available |
| At/above approved moderate threshold | Non-diagnostic care prompt after one usable night | Available |
| Independent high-confidence highlight signal, even with low snore score | Care prompt if the separately approved highlight rule is met | Available |
| Invalid/unusable recording | Explain limitations; no severity label or reassuring score | Available |
| Insufficient history for a repeated-pattern claim | No repeated-pattern claim | Available |
Approve numeric score boundaries T_moderate and T_high; none is filled in here. The meeting’s approximately 3–5 highlights is a proposal. Jonas must supply the count definition, deduplication, confidence rule, recording duration/coverage requirement and count window before management picks T_highlight. Do not transform the 10+ highlight discussion into a clinical rule or count highlights as AHI.
Suggested result copy: “These sounds may be worth discussing with a care professional. Airese cannot diagnose sleep apnea.” Button: “Request a callback”. Mild/low copy: “You can record another night to learn more about your sleep sounds.” Invalid copy: “We couldn’t produce a reliable result from this recording.” A low result must never claim that apnea is absent.
Illustrative conditions for review only:
if recording is not eligible: show unavailable/limited result
else if approved snore threshold OR approved independent-highlight rule:
show reviewed care prompt
else:
encourage another recording
manual care access stays available in each case
D-04 · What makes a recording unusable?
Current duration rule: 2–8 recorded hours, inclusive, with capture stopping at eight hours. Under two hours is ineligible for a score. The earlier six-hour proposal is superseded. Quality, recovery and short-session retention remain separate decisions.
Jonas supplies the measurable quality indicator, unit, sampling method and proposed cutoff. Kedar shows permission blocked, storage blocked, short recording, noisy recording, interruption, processing retry and valid result. At each boundary test just below, at and above the selected value. The app says recording duration, not sleep duration. Preserve recoverable artifacts and warn before destructive discard.
Choice A: hard eligibility at the approved minimum/quality bound → consistent but fewer early reports. Choice B: a clearly limited report below that minimum → more feedback but a greater comprehension risk. Recommendation for beta: no score/category/automatic threshold CTA when eligibility is unproved; keep care accessible and explain any retained measurements. Approval must settle retention, retry and short-session discard separately.
D-05 · Deleted audio
Current deletion proposal: Delete all recordings removes recordings, reports and related night data; Delete account removes identity and governed data; Logout ends the session. The earlier audio-only-retain-report proposal is historical. See the current deletion contract.
Alternative: delete the entire recording whenever audio is deleted → simpler retention contract, but users lose useful history. Retaining a waveform costs less data but can retain sensitive sound-derived detail and mislead users about playback; it is not the recommended default.
D-06 · Accounts, server data and regional care
Recommendation: use the existing account/auth tables and the five-table recording proposal; send minimum approved structured results and notes, not raw consumer audio. Derive owner from the server session on every request. Keep local data claiming explicit, fail on cross-user access and prevent deleted records from returning through retries. New routes are proposals in the engineering contract, not delivered endpoints.
SG requests remain in SG CS, MY requests in MY CCC. Shane reports SG developer access; the MY key is pending. Agree the country endpoints, payload, recipient/owner, confirmation, hours/SLA and fallback. Recommend contact/country/reference/source/consent only; health lookup needs separate access approval. A submission is not receipt and receipt is not a human response.
D-07 · Legal and launch sequence
Gary / Ervin resolve the controller, review owner and publication decision for the draft terms/privacy notice. Tuesday draft clearance is not final legal approval. Complete the processor/location/retention data sheet before publishing. Malaysia notice-language review is explicitly open.
Recommended date decision: release only after an approved freeze and required evidence, then choose the invitation date. If feature lock is mid-November, move invitations after it. If 11 November is retained, agree a feasible earlier freeze, unchanged gates and scope reductions with an estimate; do not quietly compress physical-device testing.
Screen handoff to Kedar
| Screen | Copy / states to show | Decision it supports |
|---|---|---|
| Email OTP | Email entry; sent; incorrect/expired; resend; offline; verified; returning session | D-01 |
| Report | Low; elevated; independent highlight signal; unavailable; analysis version/limits | D-02/03 |
| Recording unusable | Too short; excessive noise; interruption; available recovery | D-04 |
| History after audio-only deletion | Report/notes retained; audio absent; waveform absent; delete-recording action | D-05 |
| Deletion confirmation | Audio only versus whole recording; pending/failed remote deletion | D-05/06 |
| Care request | Explicit SG/MY; fields/consent; submit; received; unknown receipt; retry; fallback | D-06 |
The deck now uses exact V1 source screens beside each illustrated decision. Captions identify missing proposed states and differences from the current plan. Kedar must supply any new states and confirm the final approved prototype version; source sample UI is not shipped-product evidence. Capture the final prototype version, selected option, copy, formula/config version, approver and date in the decision register.
D-11 · Launch audience and distribution
Version: 2026-10-28-beta-purpose-v1. Shennan confirms the first cohort is an internal test with friends and family. Start with that group; if the landing page and marketing are ready, recruit additional volunteers who match the test profiles below. Expansion depends on evidence and support capacity.
Who we want to test with
Adults in SG/MY on supported phones, covering both profiles:
- People concerned about snoring who want information before seeking help.
- People whose partner or family has raised concerns about their snoring.
Friends and family are the first recruitment channel. For profile-matched recruitment, confirm marketing readiness, invitation consent and screening criteria. Include the phone/OS combinations and recording conditions needed to assess technical capability; do not assume the first group covers them all.
What beta should establish
| Objective | What we observe |
|---|---|
| Technical capability | Overnight capture, processing and scoring consistency; crashes, battery, memory and storage; interruption recovery and server save/reload across supported phones. |
| Complete a night | Signup → usable recording → report; completion, drop-off and failures. |
| Understand the result | Can users explain the report, its limits and next step without coaching? |
| Return to the app | Repeat recordings, drop-off and reasons for returning or stopping. |
| Reach care | Callback request → correct SG/MY CRM → CCC response; receipt, response time and duplicates. |
| Control their data | Save/reopen, storage cleanup and deletion work as described. |
Technical capability includes repeatable processing/scoring for the same inputs, correct 2–8 recorded-hour and quality handling, safe recovery, protected account ownership and accurate server-save status. Record results by build, phone and OS; report failures as well as passes. Existing device, scientific, privacy/security and care-delivery gates still apply. User feedback does not establish clinical accuracy.
Approve before invitations: batch size, test duration, profile/device coverage, support and recruitment owners, success criteria and the rule for expanding or pausing. Numerical targets remain to be agreed. Use the two real-world test rounds to find blockers and verify fixes on the release candidate.
Distribution: share the iOS TestFlight invitation link when the external-testing build is available; confirm the Android route separately. “Internal test” describes the friends-and-family cohort, not App Store Connect tester permissions.
Counterparts: decision pack, test plan, register, Phase 1 PRD, EAS-1 / EAS-3 / EAS-88.