Decision timeline

November 2026

Atenvia domain and first release

The team chose atenvia.co and an interim AirStation subdomain. Jonas will submit pricing. Gary and Ervin still need to agree the first release and engineering capacity.

Discovery plan · 24 November discussion

Snoraire’s care request needs another check

The team found that the build under review could share an older night in addition to the latest three. It could also include height, weight and BMI when available. On 18 November, sample requests reached separate Singapore and Malaysia test systems.

Shane and the regional care and privacy teams still need to agree what the app may share and what it tells users before sharing. They also need to confirm how repeat requests are queued, how working days are counted, who responds and when, and what happens if a request fails. The team still needs to test the full process with the app build intended for testers and the live care systems.

EAS-87 · EAS-125 · 2 November care transcript · 3 November engineering transcript · Notion decision timeline · Full decision register · 19 November workbook · Full review and source notes

Running costs and launch blockers

Shane agreed to send Gary the running costs at different user counts, the timeline and what could delay it by 20 November. The estimate discussed was for planning. Tracking where users come from still needs to be checked on a phone and in the live app.

Raena follow-up transcript

Private app-store testing comes before public launch

The follow-up with Raena distinguished private app-store testing from public review. January was discussed as a target for a limited public launch. The team still needs to choose between a website signup and a direct store link, get management and store approval, and confirm whether IMDA will accept beta evidence. Raena will check with IMDA.

Raena follow-up transcript

Snoraire’s wellness message and app wording

Daniel reported that management endorsed two points for Snoraire: detailed snoring analysis and access to a dedicated sleep-care coordinator. The team took a wellness approach to marketing and agreed to keep “breathing pauses” in the beta app while legal reviews the wording. Softer marketing wording is still a draft.

Kedar will pull the wording together and Daniel will review the terms used. The final claims, care referral process, terms, privacy wording and Snoraire name still need clearance.

Morning USP and legal transcript · Afternoon beta copy transcript

20 November is the target for staff testing

The team aimed to give staff access on 20 November, subject to Shane confirming the app build and who can install it. The 11 and 16 November dates were earlier targets.

17 November copy and beta transcript

Snoraire handover is still being planned

The internal review discussed closing the project after IMDA review. The follow-up with Raena discussed a mid-to-late December exit if the app stores are ready. The group also discussed a possible interim handover to Jonas and a future product manager appointment. The receiving owner, date and acceptance are still open.

17 November retrospective transcript · Raena follow-up transcript

Audrey plans to take three Atenvia options to Easmed

Audrey was preparing to present three options on 26 November, 2–3 pm Singapore time, subject to calendar confirmation. Shane and Kedar were expected to join. Easmed still needs to choose an option, name the decision owner and any build team, and confirm the grant obligations.

17 November retrospective transcript · EAS-89 · EAS-16

Keep the current score while gathering feedback

The team agreed to respond to Gary’s feedback and test with more people before changing how the score is calculated or setting new cutoffs. Suggestions included clearer wording for nights with no breathing pauses and a better way to compare results across phones.

16 November Teams transcript

Atenvia starts with discovery and planning

The engagement covers workshops, discovery and planning. The team will first review how the current systems work. At the internal kickoff, the team agreed to ask stakeholders to confirm the problem, intended users and what success looks like before starting design.

Clinic-only access, dashboards and patient records were ideas to explore. Easmed owns funding and the appointment of any future build team. Earlier build, launch and grant dates and the possible quote from Ashwin were planning inputs.

11 November kickoff transcript excerpt · Current Atenvia plan

The release review still had open items

The review carried forward the 2 November product confirmations and the 8 November readiness check. It recorded no new approval. Results wording, care routing and what the app shares, and legal and operating sign-off were still open. The 3 November privacy research informed that review. Legal approval and practical checks were still due.

The 2 November workbook focuses on 22 product and engineering decisions. The full register records 30 decisions across the project.

Release checklist · Owner confirmations · Full decision register · 2 November workbook

Raena and Shane agreed to start with a closed beta

The first round will be invite-only. Raena and Shane will revisit who can join as the app and care teams get ready.

10 November Teams transcript

Beta invitations were on hold

Four preparation checks were complete. An Android test build had been submitted to Google Play, and an iPhone build was available for internal testing through TestFlight. The team still needed to verify access for approved testers, Google Play availability and installation on phones.

Other checks covered security, moving and restoring data, overnight recording on phones, Singapore and Malaysia care requests, legal and store materials, customer support and the final launch decision. Shane owned the release and security work. Jonas supported fixes to the app and test builds. Google Play’s 11 initial setup tasks were tracked separately.

Release checklist

Private testing and website changes for beta

The team planned to keep the beta separate from the live service and send changes through product review. Marketing agreed to hide the Share button on the website for beta.

5 November Teams transcript · 5 November marketing transcript

Phone details and overnight recordings still needed rules

The team discussed requiring a phone number for care requests. The team still needed to confirm where and how to require it. The group also discussed which night gets credit when recording crosses midnight and how to handle short or multiple recordings.

4 November engineering transcript

The team chose the beta results layout

The review with Ervin selected side-by-side cards of equal weight, with the overall result and the care button easy to find. The Listen button gets extra emphasis when the app detects frequent pauses. This replaces the unequal cards proposed on 2 November.

The exact styling, what counts as frequent, final wording and checks on a phone were still open.

3 November Teams transcript · EAS-130 · EAS-88

Care requests go to each country’s own list

The team chose separate Zoho lead lists for Singapore and Malaysia, with the app’s service checking what it sends. The October notes had mentioned different record types and an external form. Regional owners still needed to confirm the destination details, who can see requests and how receipt is checked.

3 November engineering transcript · EAS-87 · EAS-125

Password sign-in was confirmed

Jonas and Shane chose password sign-in, and Shane confirmed it on 2 November. The date of the original choice was unclear. The team still needed to test account creation, email checks, password recovery, sign-out and whether each account can access only its own information.

Owner confirmations

The team approved a starting Snore Score

Shane confirmed that the meeting with Ervin had approved the provisional score. Longer and louder snoring counts more toward the score. Jonas will test it, report back and adjust it as needed. The cutoffs and medical interpretation still need separate review.

Approved method and owner confirmation

Night Notes and a bedtime reminder were confirmed for the first release

Shane confirmed approvals for morning and bedtime check-ins and a bedtime reminder. The exact approval dates were unclear. The notes stay separate from scoring. The team still needed to decide what people can enter, how notes attach to a night and whether saved notes reload correctly. Reminder timing, opt-out and delivery on a phone also needed testing.

Owner confirmations

One recorded night is enough to request a callback

The morning proposal would have shared only the night that prompted the request. Later that day, the care team chose to share up to the three most recent available nights for beta, regardless of severity. If someone deliberately requests another call, it updates the earlier record, restarts the three-working-day clock and goes into the queue by submission time. Automatic retries are handled separately.

The team still needed to agree the button wording, which personal details to share and what to tell users before sending them. It also needed to confirm the working-day calendar and who handles delays or failed requests. The app should show success only after the request reaches the care system.

2 November care transcript · EAS-87 · EAS-125

Work continued on result categories and what people can hear

The team proposed using the more serious of the snore score and breathing-pause findings to guide the result. The cutoffs, how to handle poor recordings and final wording still needed review. The proposal put breathing analysis first, then the Snore Score and the care button. The team still needed to check which clips play and what appears when there is no audio. The 3 November review chose the layout.

2 November results discussion

Recording length and audio deletion

The working rule was to use recordings from two to eight hours and stop at eight hours. That measures how long the phone recorded. Actual time asleep is a separate measure. The team still needed to check short, poor-quality and interrupted recordings.

Jonas reported that the app would keep 15 highlight clips after analysis and remove the full recording. Deleting audio should hide playback while keeping notes, results and insights. The team still needed to test deletion on phones and agree how users can delete an entire account.

2 November product discussion

Privacy review and regional signup still needed decisions

The team kept Singapore and Malaysia as the beta countries. It still needed to settle postcode versus state for Malaysia, how to handle a phone number from a different country and which details are necessary, including date of birth, gender, height and weight.

Using data for app results, joining research and sharing information with care staff are separate purposes. The privacy review still needed to settle what people see and agree to before sharing, how long data is kept and how people can have it removed. Statements in the meeting about privacy exemptions and limits on personal fields were awaiting verification.

2 November product discussion

October 2026

Atenvia reviewed possible starting points

The discussion explored starting with one Löwenstein connection, who would own the system design and which medical information could be shared with Zoho. These were questions for discovery.

29 October Teams transcript

The team discussed how to approve changes and hand over Snoraire

The internal plan called for Shane to lead product work and Jonas to lead engineering. Kedar would keep the change list in Excel, with approval by email before engineering started on scope changes. The client still needed to confirm who could approve changes, how often to review them and what to do when a decision was late.

The proposed support plan kept Raena and Kedar on product and design and Jonas on engineering after launch. The date, receiving owner and acceptance still needed agreement.

Project roles and changes discussion · Handover discussion

The team planned a simple way to ask for sleep care

Gary wanted a consistent care button and a short request process. Daniel led marketing coordination. Raena and Jonas were to brief Shu and Shahira, and Shu was to brief Singapore care staff. Hours, staffing, approved materials and readiness still needed confirmation.

A GP-first route without a paid online review was discussed for Singapore app users. Daniel’s proposed paid pathway for people arriving through Facebook ads was a separate plan. The team discussed keeping the app free to use and reaching people who might overlook snoring, as well as their partners.

29 October care transcript · Care and marketing discussion

A small invited beta and a broader rollout were discussed

The November plan was to invite friends and family to test stability, ease of use, repeat use, privacy controls and whether the care handoff worked. Dentist contacts were suggested. Group size, trial length, phone coverage and when to expand were open. January was discussed for a phased public rollout, subject to readiness.

The team planned to combine app usage data with a survey. Kedar was to draft questions about using the app and Shane was to contribute technical questions. Recruitment, consent, measures and reporting still needed agreement.

Beta and feedback discussion

Support email and campaign tracking

The beta plan kept Airese as the source name in Zoho and tracked marketing channels separately. The team targeted January to follow how people arrive at the app and request care. Consent, repeat records and how to credit campaigns still needed agreement.

The notes named no-reply@theairstation.com for verification emails and itsupport@theairstation.com.sg for technical help in both countries. A new domain was deferred. Email delivery, support ownership and backup cover still needed checking.

Support and tracking discussion

The first release remained focused on snoring

The scope kept the focus on snoring and left out a rest score, coughing and movement. What the app could say about breathing pauses needed its own review.

Automatic cleanup of phone recordings was also open, including when to remove older files, how to warn users and what to keep. That policy was separate from the user’s choice to delete recordings.

28 October product review

The team prepared ten choices for the 28 October review

The decision pack recorded options and trade-offs. The team still needed to agree who could approve changes, how to hand over Airese work to Atenvia, and when decisions were due.

At the time, open questions included account access, required personal details, Night Notes, recording length and storage, care routing and what the app shares, and how the score and results should work. The review used meeting summaries and an internal scope note. Later entries record changes to those plans.

decision pack · Notion decision timeline · Shared release concerns

The team proposed who would lead product and engineering

The internal plan put Shane on product through the first Airese release and Jonas on engineering. Shane would prepare the list of features and the screen walkthrough, add marketing and care tasks, and set up a shared Teams channel. Earlier engineering assignments still needed a new owner or confirmation.

The team discussed Ervin as final product approver. Gary would need formal delegation. The proposed handover would move Shane to Atenvia after launch and leave Airese with Raena, Kedar and Jonas. Raena and Kedar could start discovery with Pam before a formal kickoff with Audrey. The client still needed to confirm responsibilities, deadlines and handover.

26 October evening operating-model meeting · Approval record

Email codes were chosen for the first version

The daytime meeting chose accounts that use a code sent by email. The team still needed to check that people could only access their own data and that it saved correctly. Syncing to a second phone was deferred. Shane later confirmed password sign-in on 2 November.

Gary and Ervin were due to review the screens on 28 October. Kedar would prepare the designs, Shane would explain the trade-offs and Jonas would supply the scoring rules. The score, when to show breathing highlights, usable recording rules and what remains after audio deletion were open. Comparisons and trends were deferred to January. The beta invitation date and when to stop adding features still needed to be reconciled.

shared meeting note, read in Comet · current PRD

An earlier scope note described an app without accounts

The scope review described keeping audio and history on the phone and sending selected data to the service for analysis or research. The team still needed to decide what to share, who could access it, how to ask permission and how to delete it. The later sign-in decisions changed this accountless plan.

Local V1 scope note and PRD boundary (not Granola)

Recording storage and running costs

The team had asked on 12 October for Gary’s permission before moving or deleting older recordings. The 20 October discussion kept marketing spend separate from app running costs. The team still needed to agree who owns stored recordings, how long to keep them, which backups are needed and how to divide shared costs.

12 October discussion · 20 October cost discussion

Keep care requests in each country’s own Zoho system

The team preferred to keep each country’s leads in its own Zoho system for November. It planned to map the full care process before changing routing or shared access. A Malaysia-first approach and access to both lists were ideas for later. Who could see requests after handover was still open.

Multi-country CRM routing and data flow with Wei Jian

The team briefly moved away from a sign-in screen

The plan removed sign-in and sign-out from the first release while keeping verified email and required contact details during setup. Phone verification was deferred. The 26 October and 2 November account decisions later changed this plan.

Busy

Use saved contact details for callbacks

The app would reuse profile details, send the request to Zoho and show confirmation. The team still needed to check access, which details to send, how to confirm receipt and which country receives the request.

Busy

Night Notes were initially deferred

The team wanted a simpler first version and a separate design for later features. It deferred Night Notes at this point. Shane confirmed their inclusion on 2 November.

Busy

The team proposed putting the score first

The design put the score first, followed by a short title, explanation and next step. Three result categories were still the working model. The category and card choices and final copy needed review from Gary and Erwin.

Busy

Three scoring methods were under review

The team recommended using 30-second samples and a simple beta score. Gary and Erwin were asked to choose a method by 21 October. Final cutoffs and clinical validation remained open.

Busy

The team planned to test recordings on phones

The team planned separate test and live data, automated checks of the app flow and recording tests on phones. It discussed testing newer phones first, with the final list of devices and operating systems still open.

Busy

Launch scope and measures of success needed agreement

The client needed to agree what would ship, who would make decisions and how success would be measured. November for Airese and February for Atenvia were discussion targets. User counts and reviews were examples of possible measures.

Easmed MVP scope, success metrics, and delivery model with Audrey

Shane would keep a shared delivery tracker

Shane would track work across Airese and Atenvia and review it at delivery meetings. Where to keep the tracker, when to stop adding features and who would approve the scope were still open.

Catchup on Easmed handover

The first proposal kept setup simple

The team planned to skip email and phone verification, use phone as the main callback contact and ask people to agree to the terms. On 13 October, the team brought back verified email and more profile details.

Onboarding flow and recording details design with Kedar

People should be able to lock their phone while recording

The team planned to let people lock the screen during recording and reopen the app to finish analysis. It would then open the results directly. The discussion mentioned a 12-hour stop, a possible eight-hour default and an estimated wait for results. These were early plans.

Onboarding flow and recording details design with Kedar

Three result labels were proposed

Ordinary, Unusual and Repeated pattern were proposed as labels to guide the wording and the invitation to seek care. The numbers behind the categories and the definition of a repeated pattern were still open.

Onboarding flow and recording details design with Kedar

The early plan included Night Notes

The team wanted a journal separate from the score and was still deciding where to put it. The 13 October discussion deferred it. Shane confirmed its inclusion on 2 November.

Onboarding flow and recording details design with Kedar

Keep the bedtime reminder and manual deletion

The team planned to defer reminders to stop recording or check results, along with automatic cleanup. Reminder timing and how long data should be kept still needed agreement.

Onboarding flow and recording details design with Kedar

Marketing discussed how to describe Airese

The discussion explored sleep screening and a sleep companion as possible descriptions. Claims about AI and safe or dangerous results needed review before publication. The FAQ, privacy notice and terms were still being prepared.

Marketing Launch Airese

The team explored who should receive requests in each country

The early plan kept Singapore requests with Singapore care and Malaysia requests with Malaysia care. The group also discussed sending all requests to one team with a country label. Shahira was to document how app requests should be handled. Access and source tracking stayed open.

Airese app customer handoff workflow and CRM integration with Nur Shahira

The team planned to analyse recordings on the phone

The proposal kept contact details separate from sleep analysis and allowed the records to be linked where approved. The team needed to agree which health information, if any, could go to Zoho and verify those protections.

App deployment to AWS, data architecture, and customer handoff workflow

The app needed to be open to finish analysis

The initial rule asked people to reopen the app for the last step. About 15 seconds was discussed as an estimate. The team still needed to measure the wait and test recovery if processing stopped.

Easmed sleep app MVP design and onboarding flow with Kedar

September 2026

The first Zoho tests used limited access

The team planned to use a connection with limited permissions to test reading records. It shared the setup for testing. Successful reads and live access still needed checking.

Zoho One API setup and PostHog analytics integration