Working evidence · reconciled 11 November 2026

Airese Phase 1 PRD reconciliation

Current decisions and release evidence — reconciled 11 November 2026

Version: 2026-11-11-decision-checkpoint-v1. Password sign-in, the provisional formula, Night Notes and the bedtime reminder are approved choices under 2026-11-02-owner-confirmation-v3. Their implementation and testing remain separate acceptance work. Exact original approval dates retain the limits recorded in the owner confirmations.

The last beta assessment is 2026-11-08-beta-release-preflight-v5: hold invitations. Four preparation gates are complete; store distribution is partial and six other gates remain unfinished. Android 0.1.10/26 and iPhone 0.1.10/32 were submitted. Tester access, physical installation, overnight acceptance and operational approval remain open. Shane owns deployment and DevSecOps; Jonas supports application/build defects.

D-07 privacy research was completed on 3 November; legal endorsement and implementation acceptance remain open. Historical 28 October reviews and the 11 November invitation target do not establish a current deadline or permission to invite. Remaining product decisions include result categories/copy and the regional callback/CRM contract. No requirement, owner, acceptance criterion or ticket status is changed by this presentation update.

Read the owner confirmations, beta checklist and reconciled decision timeline.

Earlier dated planning — historical where superseded

Current owner confirmation — 2 November 2026

Version: 2026-11-02-owner-confirmation-v3. Read the current confirmed decisions first. Shane confirms password sign-in decided by Jonas and Shane (D-01), the current provisional formula approved last week in the Ervin meeting with ongoing Jonas testing/tuning (D-02), and Night Notes plus bedtime reminder approved for MVP last week (D-28/D-29). Exact historical dates were not supplied.

D-06/D-15/D-21/D-26/D-27/D-20 await today’s meeting confirmation. D-07 research is due Wednesday, 4 November. D-25 result hierarchy joins today’s approval priorities. Earlier conflicting approval-status and MVP-inclusion wording below is historical. Formula approval is separate from category bands, clinical/device validation and release acceptance. No ticket closes solely because these records change.

Current UI and acceptance review — 2 November 2026 v2

Version: 2026-11-02-ui-granola-v2. Read the latest reconciliation first: it compares substantive 2 Nov Granola notes with V1 source 7ab0733, updates the current decision register to 30 records and specifies 16 acceptance review areas. Earlier conflicting requirements/proposals below are historical. Proposed thresholds and prototype behavior are not approved requirements. Notion property reconciliation remains pending reliable access; the existing EAS-26/27 device and privacy/release gates remain.

Latest decision reconciliation — 2 November 2026

Version: 2026-11-02-granola-refresh-v1. Current Excel decision log; source reconciliation and open decisions. The workbook contains the current review log, all 19 concerns, prior decision history and source evidence. The 29 October account/password and audio-only deletion discussions conflict with earlier proposed contracts. SG Deals versus Leads and API versus form wording also need confirmation. These are recorded conflicts, not approved requirement changes. November remains an invited technical beta; January is the broader launch direction. Final approvals and acceptance evidence remain pending.

Earlier dated content in this document is historical where it conflicts with the refresh. Notion alignment is pending access; no release, implementation or clinical/legal acceptance is established here.

Current beta cohort and objectives · 28 October 2026

Version: 2026-10-28-beta-purpose-v1. Shennan confirms the first cohort is an internal test with friends and family. Start with that group; if the landing page and marketing are ready, recruit additional volunteers who match the test profiles below. Expansion depends on evidence and support capacity.

Who we want to test with

Adults in SG/MY on supported phones, covering both profiles:

Friends and family are the first recruitment channel. For profile-matched recruitment, confirm marketing readiness, invitation consent and screening criteria. Include the phone/OS combinations and recording conditions needed to assess technical capability; do not assume the first group covers them all.

What beta should establish

Objective What we observe
Technical capability Overnight capture, processing and scoring consistency; crashes, battery, memory and storage; interruption recovery and server save/reload across supported phones.
Complete a night Signup → usable recording → report; completion, drop-off and failures.
Understand the result Can users explain the report, its limits and next step without coaching?
Return to the app Repeat recordings, drop-off and reasons for returning or stopping.
Reach care Callback request → correct SG/MY CRM → CCC response; receipt, response time and duplicates.
Control their data Save/reopen, storage cleanup and deletion work as described.

Technical capability includes repeatable processing/scoring for the same inputs, correct 2–8 recorded-hour and quality handling, safe recovery, protected account ownership and accurate server-save status. Record results by build, phone and OS; report failures as well as passes. Existing device, scientific, privacy/security and care-delivery gates still apply. User feedback does not establish clinical accuracy.

Approve before invitations: batch size, test duration, profile/device coverage, support and recruitment owners, success criteria and the rule for expanding or pausing. Numerical targets remain to be agreed. Use the two real-world test rounds to find blockers and verify fixes on the release candidate.

Distribution: share the iOS TestFlight invitation link when the external-testing build is available; confirm the Android route separately. “Internal test” describes the friends-and-family cohort, not App Store Connect tester permissions.

Earlier dated proposals are historical where they conflict with this update.

Management review update · 28 October 2026

Version: 2026-10-28-management-review-v1. Shennan approved these four documentation updates after reviewing the 23–28 October chat. Policy values and clinical thresholds remain open.

Earlier dated records remain historical where they conflict with this update. No implementation, device acceptance or release approval is added.

Accounts, deletion, release data and CRM flow · 28 October 2026

Version: 2026-10-28-account-data-crm-v1. Source: Shennan’s current clarification and supplied deletion-flow context. Account signup with email verification is the current direction; accountless setup is superseded. SMS verification depends on Malaysia Twilio provisioning and verification, with no committed completion date. This replaces January as a fixed SMS assumption.

Deletion proposal for the account flow

The menu contains Delete all recordings, Delete account and Logout. Delete all recordings removes every recording, report and related night data in the declared local/server scope, while keeping the account. Delete account removes the identity and governed data and revokes sessions. Logout ends the session without deleting the account. The accountless alternative is historical, not a current option.

Use a full-height confirmation sheet: Delete all recordings? “All recordings, reports and related night data will be permanently deleted. This can’t be undone. Save any reports you want to share with a medical professional first.” Buttons: Keep recordings / Delete all recordings. After confirmed deletion, Reports shows No recordings yet and Record tonight. Preserve honest pending/failed remote status, block stale retries and define the separate research/CRM erasure process. Management still needs to approve the exact deletion scope and provider retention exceptions; this replaces the audio-only-retain-report proposal as the recommended menu.

Three release/data boundaries

Use separate endpoints, credentials and permissions. The diagrams describe intended boundaries, not evidence that the environments are deployed or that storage/payload controls pass.

Direct CRM handoff for Thursday 29 October

Submit callback requests plus agreed sleep-result context directly through CRM APIs, not webforms. SG and MY write to separate CRM databases within their respective Leads / Deals constructs. CCC is intended to have read access to both. Confirm country selection, permitted result fields and consent, the Lead-to-Deal mapping, receipt, access roles, response promise, duplicate prevention and fallback with CCC. Decide what happens for users outside SG/MY; do not silently reroute. Singapore payment/booking is removed from this handoff approval.

Distribution and pack layout

For iOS, share the TestFlight invitation link after the build is available for external testing; Apple’s external group and beta review requirements still apply. Android needs a separate route. Apple guidance. The standalone test-plan section is removed from the meeting pack only; existing device/security/privacy/operational acceptance gates remain in the linked test plan. Timeline title: Path to 11 Nov launch.

Recording duration and score illustration · 28 October 2026

Version: 2026-10-28-duration-and-simulator-v1. Shennan sets the recording boundary to 2 hours minimum and 8 hours maximum, inclusive. Below two hours, no eligible score. Stop capture at eight hours. Audio-quality rules remain a separate requirement. These are recording hours, not measured sleep. This replaces the earlier six-hour eligibility proposal; it does not define short-session discard or recovery behavior.

Test 2h minus one second, exactly 2h, exactly 8h and the attempted 8h-plus-one-second boundary. Capture must not continue beyond the maximum. Existing three-night device acceptance gates remain unchanged; this document update is not an implementation pass.

The portal shows the recommended clamp formula as LaTeX and plain English. Its interactive scenario varies recording hours (2–8), episode minutes, a single relative sound level applied to all episodes, and a provisional scaling cap. The 8/18 dB relative bands produce weights 1.0/1.1/1.2. The default 8h, 60-minute, 12 dB scenario gives Pw=13.75% and about 40.8 points at cap 82.5. This is hypothetical, not a workbook result or a clinical-severity simulation. Moving the cap does not approve a threshold or change the production formula. 82.5 remains provisional and unapproved.

Version: 2026-10-28-score-recommendation-v1. Source: Shennan’s correction. Recommend the later background-relative formula with the clamp, rather than the historical 80/20 blend.

Score = 100 × sqrt(clamp(Pw, 0, 82.5) / 82.5)

Pw = 100 × sum(episode duration × mean snore weight) / recorded audio time.

Use duration-weighted snore weights 1.0 / 1.1 / 1.2 at 8 / 18 dB above background. Episode spans include quiet gaps. These are relative signal inputs, not calibrated physical loudness.

The 82.5 cap remains provisional. Confirm the final parameters, quality exclusions and missing-noise behavior, then validate on compatible recordings and supported phones. The supplied workbook lacks this candidate’s required inputs; no measured result or clinical approval is implied. Keep breathing highlights separate. The older 80/20 ring is a historical comparison only.

This supersedes earlier recommendation wording. Historical formulas, reproduced results and existing acceptance gates are unchanged.

Current MVP scope · 28 October 2026

Version: 2026-10-28-mvp-approval-v1. Source: Shennan’s direct update on 28 October, recording Ervin’s scope decisions and the team’s tagger observations. This supersedes conflicting earlier proposals; it does not select a formula or prove implementation.

Older formulas and original prototype screens remain reference material. Their dB values, extra metrics and sample copy are not approved MVP claims.

Current launch approval plan: three tracks to 11 November. Intermediate dates remain proposed; acceptance evidence is still required.

Latest meeting · 27 October 2026

Version: 2026-10-27-meeting-v1. The latest meeting record and current-first launch plan supplement record direct Zoho API direction, SG SCC/MY CCC handoff questions for 29 October, report flowchart and product decisions for 28 October, and Daniel/Maha marketing actions. Full transcript retrieval is unavailable; the evidence is Granola’s AI summary.

Mid-November beta and January/February public launch remain plans to reconcile with the 11 November target and feature lock. Cohort size, response promise, permitted CRM health fields, local-audio/remote-analysis wording, SMS timing and Shane’s UTM implementation assignment need explicit confirmation. Existing product, device, scientific, privacy and release gates remain. This supplements 2026-10-27-launch-plan-v2; the Excel v3 workbook now includes the same supplement. Saved Notion alignment.

Launch work plan update · 27 October 2026

Version: 2026-10-27-launch-plan-v2. The canonical launch work plan and updated Excel tracker now make all 19 concerns from the supplied 23 October message explicit.

The tracker separates 19 summaries from 89 work items. It links 78 existing Notion tasks and adds 11 explicit proposals. Each concern has product work, engineering work, context, dependencies and required evidence. The plan uses Simplified Technical English.

This is a planning clarification. It selects no formula, threshold, retention rule, location service or release date. Full email OTP remains the baseline. Comparisons and SMS verification remain January work. External research is conditional. The existing EAS-26/27 device criteria remain unchanged.

Recorded Notion dates and estimates are not new commitments or verified remaining effort. Confirm scope, reviewers, engineering estimates and capacity before fixing the freeze, test and invitation sequence. Summary rows do not add effort to their linked tasks.

Notion alignment and saved readback are recorded in the canonical plan. The generated dashboard snapshot remains unchanged.

Completeness review · 27 October 2026

Version: 2026-10-27-completeness-v1. Evidence and delivery supplement; unsynced Notion packet.

The freshly read 26 October evening note records Shane focusing on PM and Jonas owning engineering. Prior database/API implementation assignments for Shane need reassignment or explicit reconfirmation. Shane coordinates the freeze list, screen walkthrough and cross-functional deliverables. Maha is the recorded marketing owner; Shahira’s 8 October care-SOP assignment needs current-status confirmation.

The internal note reports Ervin as final product authority, with formal delegation required for Gary to exercise that mandate. Confirm and capture authority, decision outcome/rationale, affected requirements, exact approved versions and actual date at the 28 October review. The product baseline below remains email OTP. The evening authentication discussion assigns the engineering trade-off to Jonas without expressly revoking that baseline or establishing a legal conclusion.

The register now includes options, trade-offs, rationale, decision targets and affected requirements. No new client approval, test pass, deadline commitment or release decision is recorded. Notion is unsynced for this supplement because no writable route/current page read is available; the exact affected pages are in the update packet. Prior 26 October readbacks remain dated evidence.

Current plan · 26 October 2026

Version: 2026-10-26-signoff-v1. Source: 26 October minutes, supplied by Shane and checked against the shared Granola note in Comet. PRD current decisions, app scenarios, and operations.

Full email OTP accounts supersede the 23 October accountless boundary. Authentication, account-linked consent, user ownership on every API route and the confirmed production payload require implementation and evidence. OTP reuse and SG CRM access are reported, not newly validated. Malaysia access awaits Wei Jian. Second-phone sync is deferred, with architecture support required later.

Gary and Ervin review screens on Wednesday 28 October; Kedar prepares copy/logic, Shane explains trade-offs and Jonas supplies technical logic. Ervin is the requested score approver. Weighted snoring time/loudness stays separate from high-confidence breathing highlights. Exact formula/bands, Ordinary/Unusual/Repeated Patterns, proposed one-night CTA and approximately 3–5-highlight trigger, approximately six-hour usable recording versus the separate reported two-hour cancellation setting, and deleted-audio analysis/waveform persistence remain open. No clinical cutoff is approved.

Comparisons, minimum-night/averaging rules, trend CTA refinement and SMS verification move to January. Pause-count development is deferred from beta; its exact date is open because the source also describes possible score inclusion after January. Beta tests technical function, CCC conversion and distribution, not public demand. The 11 November target conflicts with proposed mid-November feature lock and must be reconciled on Wednesday. Real-world and server-sync evidence is missing; existing EAS-26/27 gates remain unchanged.

The affected Notion tickets and launch checklist now carry this version. See the meeting record and reciprocal ticket links and exact acceptance text/readback. Previous content and ticket properties were preserved except the five explicitly revised Acceptance Criteria fields; no ticket was closed.

Wednesday working drafts · 2026-10-26-draftpack-v1

The draft decision deck and editable pack turns Shane’s to-dos into review material: decision/screens/copy, deleted-audio policy, data/API contract, two-round testing, terms/privacy and unsent handoffs. This includes a proposed policy to retain approved reports/notes while deleting audio/clips/waveform; it is an option for approval, not a changed requirement. The score candidate is a dated source observation with provisional values, not selected/validated methodology. Recorded baseline remains 2026-10-26-signoff-v1. No new ticket acceptance criteria, approved thresholds, release date or legal status are set by this draft pack.

Current decision and acceptance map

C-02 · Recording contract / FR-03–06 · Preflight / capture / processing

C-03 · Measures and interpretation / FR-07–09 · Report / insight

C-04 · History and Night Notes / FR-09–10, FR-13 · History / notes / reminder

C-05 · Callback and regional operations / FR-11–12 · Care request

C-06 · Analytics and success / FR-15 · Funnel / dashboard

C-07 · Support and launch operations / FR-16 · Help / launch

C-09 · Physical-device acceptance / FR-03–09 · Signed build

C-10 · Markets and beta access / FR-01–03, FR-16 · Invite / store

C-11 · Design and content acceptance / FR-01–16 · Screen inventory

C-12 · Scope and estimates / FR-01–16 · Delivery baseline

Historical records below

Earlier dated plans and evidence remain historical where superseded above. In particular, the accountless boundary and V1 comparisons are superseded; prior source/CI/PR observations retain their dates and limits. No ticket is closed by this update.

Current learning roadmap · 26 October 2026

Plan version: 2026-10-26-learning-v1. The product roadmap, learning loop and journey questions are now present in the Phase 1 PRD. This implements visuals 1–3 from the visual specification; visuals 4–6 remain later additions dependent on source reconciliation or actual findings.

V1 is the beta launch. V1.5 improves the experience using beta feedback and can include several smaller releases and experiments. Product V2 is the January/February 2027 launch direction, bringing back features deprioritised from the original scope. Each phase answers questions inherited from its predecessor and hands new or unresolved questions to the next. Learning continues after V2. Product V2 is distinct from the document filename v2.html.

The original deferred-feature inventory still needs reconciliation; no individual feature is assigned here. Methods, samples, observation windows, thresholds, review dates and findings remain proposed or open. The accountless/device-local V1 boundary, existing feature acceptance criteria and EAS-26/27 device gate remain in force. The experiment loop and record are working proposals, not completed studies or new instrumentation.

Planning notes on EAS-1 and EAS-4 share this plan version. Saved readback confirmed the notes and retained previous content and ticket properties, including statuses, owners, dates and acceptance criteria. No dashboard snapshot was edited. The baseline requirement reconciliation below retains its own version. PRD and loading checks pass. Desktop roadmap rendering was reviewed locally in Comet f.; the hosted visuals were also observed in the existing m. session. The f. hosted session requires Vercel access. No deployment or access setting was changed. Final Notion browser layout review timed out, although saved text and properties were verified. Narrow-screen, print and screen-reader review remain open.

Version: 2026-10-23-phase1-v3 · 23 October 2026

Canonical Phase 1 page: TAS Portal PRD. This record and the affected Notion tickets share this version. Local preview: http://127.0.0.1:8771/prd/v2.html#decision-contracts. The local preview is not a team publication.

V1 has no consumer accounts and keeps recordings/history on the phone, as confirmed by Shennan on 23 October. Intended production DB submissions still require an approved payload, identifier, protection and erasure contract. Research R2 uploads have separate consent. Accountless does not mean anonymous or that nothing leaves the phone.

The Phase 1 page now reconciles setup, journeys, 16 feature requirements, quality/security, data lifecycles and design handover with that boundary. Historical account-first and 12-hour suggestions are superseded direction, not new approval. Existing ticket properties, owners, dates, priorities and acceptance gates are preserved.

Editorial update · 23 October

The HTML now presents the experience in connected prose, with proposals, confirmation questions and detailed review notes behind an info button beside the relevant section. The five journey steps are expanded initially. The introductory revision paragraph and the paragraph assigning analytics measures and targets to named reviewers were removed at Shennan’s request.

This changes presentation and wording, not scope, formulas, approval status or acceptance thresholds. The existing Notion reconciliation remains the requirements counterpart for version 2026-10-23-phase1-v3; this editorial pass does not create a new ticket decision or close any work. The decision map, evidence requirements and review responsibilities remain available in section information and in this record.

The PRD and loading checks passed. Desktop rendering and the section popover were checked in Comet’s f. profile, including opening and Escape dismissal. Mobile devices and screen readers were not tested. The updated HTML has not been published.

Experience graphics

The experience now includes five line illustrations within the existing journey, a recording and interruption diagram, a report diagram separating acoustic measures and calculated scores from personal context, and a callback diagram distinguishing a tap, submission, destination receipt and human response. The figures reuse the current requirements and leave confirmation notes in the existing section tooltips. They add no scoring values, duration promises or approved product scope.

The illustrations use inline SVG; flow diagrams use labelled HTML figures and ordered steps, with stacked layouts at narrow widths. No dependency or runtime diagram renderer was added. The journey, recording and callback visuals were inspected on desktop in Comet’s f. profile. Browser access became unavailable before the report and narrow-layout visual checks; those remain unchecked. Structural PRD and loading checks passed. This update is local and unpublished.

Accordion readability

Accordion content now explains the purpose and expected behaviour of each feature, care-flow stage, quality check, distribution step, acceptance review, release stage and risk. The previously empty tester-access and supported-version items have explanatory content. Metric, access and governance accordions in the section tooltips also have context alongside their existing decisions and reviewers. The main journey has fuller explanations beneath its illustrations.

This is an editorial expansion of existing requirements and boundaries. The 16 feature acceptance blocks, requirement IDs, reviewer fields and device thresholds remain intact; no new scope or approval is recorded, so the existing Notion requirements reconciliation remains applicable. The removed Ticket reference and Design handover sections remain removed. PRD, loading, anchor and content-preservation checks passed. Expanded requirement prose and paragraph spacing were inspected in Comet’s f. profile. Mobile and screen-reader checks were not repeated, and the update has not been published.

Editorial update · 26 October · management readability

The page now opens with a management brief: the ask, four headline figures, six decisions for management with a recommendation and decision-maker each, current status, top risks and exclusions. Sections are reordered so management reads product, experience, rollout, risks and approvals first; detailed specifications, requirements, quality, data, build, release gates and the decision map follow under an appendix divider. Goals, scope and beta access terms now show visible tables drawn from the existing section information. Risk and rollout items are open by default, and each risk states its mitigation from the existing required decision. Main-path prose was rewritten in plain language and several garbled phrases were corrected.

The brief’s recommendations (measurements-only fallback if scoring is not approved, contact and consent only in Zoho by default) restate existing proposals; they are not new approvals. Requirement IDs, acceptance blocks, device thresholds and section information are unchanged, so the Notion reconciliation for 2026-10-23-phase1-v3 still applies. PRD and loading checks passed; desktop rendering was checked in headless Chrome. Mobile and screen-reader checks were not repeated. The update is local and unpublished.

Decision and acceptance map

Each item needs a named acceptance authority, written outcome and date. PRD C-01–C-12 IDs differ from launch concerns C01–C19.

C-02 · Recording contract

C-03 · Measures and interpretation

C-04 · History and Night Notes

C-05 · Callback and regional operations

C-06 · Analytics and success

C-07 · Support and launch operations

C-08 · Data lifecycle by environment

C-09 · Physical-device acceptance

C-10 · Markets and beta access

C-11 · Design and content acceptance

C-12 · Scope and estimates

Evidence and limits

Notion alignment

Read current tickets before editing. Add only the relevant reconciliation scope and cross-references; preserve all existing properties and acceptance criteria. Update/readback outcomes are recorded in the adjacent sync record.